









Construction and completion 4‐lane divided highway , total length 9km , one Interchange, five underpasses. In addition to secondary roads with length of 15km.
Excavation: 3,160,000 m3
Fill: 2,750,000 m3
Reinforced concrete: 40,000 m3
Asphalt works: 615,000 m2
Project is completed